Wet area · full system

Shower tile, start to finish.

A shower is the hardest tile assembly in a house because it holds water on purpose. Every phase below assumes the worst: the pan leaks if the pre-slope is flat, the walls wick if the membrane stops at the curb, and the bottom row cracks if you start setting from an unlevel pan.

9
Phases
5–8
Working days
Pan membrane
Hardest step
24 hours
Flood test
Tools you will need
  • Tape measure and pencil
  • 4 ft level and 6 ft straightedge
  • Margin trowel and notched trowels (1/4x1/4, 1/4x3/8, 1/2x1/2)
  • Mixing paddle and drill
  • Wet saw with a porcelain blade
  • Diamond hole saw for the valve and showerhead
  • Grout float, sponges, two buckets
  • Utility knife, nippers, grout saw
  • Lippage clips, wedges and spacers
  • Chalk line and a straight ledger board
  • Knee pads, eye and ear protection
What to buy0/12
Plain words · what the jargon means
Thinset
The cement glue that sticks tile to the wall or floor. It comes as a powder you mix with water.
Mastic
Ready-mixed glue in a tub. Fine for a dry backsplash, never in a shower or tub surround.
Slake
A 10 minute rest after the first mix so the water soaks into the powder, then you stir again.
Notch
The tooth size on the square-notched trowel. A bigger notch leaves thicker ridges of mortar.
Back-butter
Spreading a thin flat layer on the back of the tile so it grabs the ridges on the wall.
Coverage
How much of the tile back actually touches mortar. 80 percent in dry rooms, 95 percent in a shower.
Pot life
How long a mixed bucket stays usable. Past that it is dead, not just thick.
Skinned over
A dry film that forms on spread mortar. Tile will not bond to it, so scrape it off and recomb.
Lippage
One tile edge sitting proud of its neighbour, enough to catch a fingernail.
AFF
Above finished floor: the height measured once the new tile is actually down.
Substrate
Whatever sits under the tile: backer board, drywall, plywood or a slab.
01

Survey & plan

Half a day0/4 done

Everything downstream keys off three numbers: the drain center, the valve height and where the grout lines land.

Measure the wet area, not the old tile

Record the back wall width, both side wall depths, the curb length and the ceiling height at three heights on each wall. Walls are rarely plumb, and a 3/4 inch bow over five feet changes where your edge cuts land. Note the drain center measured to two walls.

  • Width and depth at three heights
  • Drain center to each wall
  • Valve center above finished floor

Watch · Measuring to the old tile face instead of the framing puts every dimension off by the thickness of the old bed.

Fix the plumbing heights now

Valve center sits 42 to 48 inches above the finished floor: 48 inches suits most adults, lower for a tub-shower. The showerhead outlet sits 78 to 84 inches up. Mark both on the studs in pencil, and check the trim spec sheet for its rough-in depth before the walls close.

  • Valve center 42–48" AFF
  • Showerhead 78–84" AFF
  • Grab bar blocking 33–36" AFF

Watch · Measuring from the old floor before the new pan adds an inch and a half, and the trim escutcheon no longer covers the hole.

Choose tile, module and pattern

Tile size sets the drain position relative to grout lines, the niche size and the height of the bottom row. Run the wall in the layout studio: no cut narrower than a third of a tile at any corner, full tiles at outside corners, grout lines aligned around inside corners.

  • Cuts at least 1/3 of a tile
  • Drain centered in a tile or on a joint
  • Grout lines carry around corners

Build the takeoff before you shop

Order tile at 10 to 15 percent over the measured area plus a spare box, and buy it all in one order from one dye lot. A second order three months later will not match, even in the same color name.

  • One dye lot
  • 10–15% overage
  • Spare box stored dry

Checking your access…